|
The Swanage Railway Trust owns three Bulleid coaches and has a
long (originally 99 year) lease on another. It has long been the
Trusts intention to restore these vehicles to traffic and this
has been the subject of fund raising for a number of years. The
Trust is now able to make a cautious start on this project
having raised a little over £20,000. However, continued progress
is entirely dependent on securing additional funding. Three of
the Trust's four vehicles are from 'Bournemouth Line' sets build
for trains from the region to Waterloo. These vehicles are
unique amongst former Southern Railway vehicles in having a
'skirt' that extended the body side to below the running board.
The fourth vehicle is also of a design that formed part of these
sets but is from a later batch build without the skirt.
The four vehicles comprise two Semi-Open Brake Thirds (4365
and 4366), a Corridor Composite (5761) and a Third Open (1457).
The first three were acquired in a substantially complete
condition. However, the Third Open lacked seats when it arrived
at Swanage but material from similar vehicles has gradually been
obtained and stored to enable an authentic restoration in due
course.
The four vehicles differ greatly in their condition: 4365 is
ostensibly well preserved but has recently deteriorated
following storm damage to the canvas roof. 4366 is in poor
condition although the interior was removed and store some time
ago so the damage is reversible. The condition of the other two
vehicles is generally good and they have been sheeted over to
ensure that this remains the situation when restoration starts.
The decision on which vehicle to restore with the available
funds was eventually relatively straightforward; 4365 was
complete and in need of recent damage being addressed but not
such a large project as to represent unacceptable risk. This
view was ironically reinforced by the poor condition of 4366 as
work on the identical 4365 would provide patterns and valuable
insights for this vehicle.
At this stage, any restoration of heritage vehicles will
essentially be a 'non-core activity' given the railways
investment in the Mk 1 fleet. As such, any project can have only
limited access to facilities with most work expected to be
carried out in the open. Given these constraints it was decided
that some professional assistance would be beneficial in
speeding up work on the exterior as well as providing welding
and related skills.
Work started on 4365 in early July and is expected to run
through to late autumn when it will be suspended until the
spring as there is a heavy program of overhaul planned for the
main service fleet. The progress reports on the right provide up
to date information. Additional assistance is particularly
welcome on this project and no special skills are needed. Please
contact the project manager.
Thank you for your interest &
support in our project. |